D
Dave
I have a question regarding tracking actual start, finish and work. Here's
an example:
Planned start: April 10, Planned Finish: April 15 (5 working days), Planned
work: 80 hours (between 2 resources @ 100% each)
Actual start: April 10, Actual Finish: April 12, Actual work: 60 hours
(between 2 resources).
This is an example that I can't get to work because when I enter the actual
start and finish it calculates the hours it took, and when I enter the actual
hours it changes the actual start and finish.
I have a feeling this has a basic answer but I'm fairly new at this.
Thanks in advance.
Dave
an example:
Planned start: April 10, Planned Finish: April 15 (5 working days), Planned
work: 80 hours (between 2 resources @ 100% each)
Actual start: April 10, Actual Finish: April 12, Actual work: 60 hours
(between 2 resources).
This is an example that I can't get to work because when I enter the actual
start and finish it calculates the hours it took, and when I enter the actual
hours it changes the actual start and finish.
I have a feeling this has a basic answer but I'm fairly new at this.
Thanks in advance.
Dave