"Actual Value" does not refelect on "Project Center" view

A

Aroh Shukla

Dear all,

1) I created a project and created 2 resources (team members) with
associated "Cost" and "Actual Cost".
For e.g. for each resource, "Cost" will be $100/per day

Total "Cost" of Project = $20K ($10K for each resource & no admin cost)

2) I also modified the view so that in "Project Center", "Cost" and "Actual
Cost" is reflected. By Default, in "Cost" column $20K is reflected and
"Actual Cost" is $0.

3) A team member update his tasks, and update the timesheet. But he could
not finish his task and took 1 day more to finish. Then he submitted
timesheet to Manager.

Ideally, the project Manager should see "Actual Cost" for team members' cost.
But "Actual Cost" always shows $0.

Am I doing something wrong and there is some other way to achive it?

Thank you in advance.
Aroh
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top