A
Aroh Shukla
Dear all,
1) I created a project and created 2 resources (team members) with
associated "Cost" and "Actual Cost".
For e.g. for each resource, "Cost" will be $100/per day
Total "Cost" of Project = $20K ($10K for each resource & no admin cost)
2) I also modified the view so that in "Project Center", "Cost" and "Actual
Cost" is reflected. By Default, in "Cost" column $20K is reflected and
"Actual Cost" is $0.
3) A team member update his tasks, and update the timesheet. But he could
not finish his task and took 1 day more to finish. Then he submitted
timesheet to Manager.
Ideally, the project Manager should see "Actual Cost" for team members' cost.
But "Actual Cost" always shows $0.
Am I doing something wrong and there is some other way to achive it?
Thank you in advance.
Aroh
1) I created a project and created 2 resources (team members) with
associated "Cost" and "Actual Cost".
For e.g. for each resource, "Cost" will be $100/per day
Total "Cost" of Project = $20K ($10K for each resource & no admin cost)
2) I also modified the view so that in "Project Center", "Cost" and "Actual
Cost" is reflected. By Default, in "Cost" column $20K is reflected and
"Actual Cost" is $0.
3) A team member update his tasks, and update the timesheet. But he could
not finish his task and took 1 day more to finish. Then he submitted
timesheet to Manager.
Ideally, the project Manager should see "Actual Cost" for team members' cost.
But "Actual Cost" always shows $0.
Am I doing something wrong and there is some other way to achive it?
Thank you in advance.
Aroh