we input "actual work" hours in the resource usage view
which automatically inputs the same hours in "work"
cells. If we make a mistake (i.e. put he actual work in
cells in the future, and later want to change the input
on "actual work", we can change the values to "0 hrs" so
as to not effect actual cost; however, it does not allow
us to totally clear the cell, and thus we end up
with "work" in a date in the future and it will hold that
date which effects finish dates. Our workaround is to
completely remove the resource and re-input the data, but
it's a pain in a longer and many resources type schedule.

Is there a way to clear the cells?
 
J

Jan De Messemaeker

Hi again,

Did you hope to get three different answers?
When I put work to zero in the final period it reverts to empty.
AFAIK, there is no effect on any schedule of the 0 in the middle.
HTH
 