C
ccgsuper
Scenario:
Multi-phased project that delivers finished units in groups as they are
completed. Contracturally, the units are to be delivered in groups on
specific dates (7 total). Each unit's logic is virturally the same with a
few minor exceptions. I have included several text columns to break down
Area, Type, Option, Variation, Unit No., Group, and Construction Sequence.
My schedule shows 10 groups comprised of 74 units. The early finish dates
are 6-12 months ahead of the contractural completions dates. Naturally, I
want to finish by the early finish dates and naturally, I want to show the
owner the contract completion dates. I have been including an activity
called "Administrative Closeout" linked between the next to the last
scheduled activity and the last scheduled activity of each unit, with a
duration equal to the finish slack between the early finish and the
contractural (late) finish date of that unit. The problem is when I do this,
almost every activity in each unit's logic becomes critical path.
I know this isn't an uncommon problem, so I'm looking for suggestions.
ccgsuper
Multi-phased project that delivers finished units in groups as they are
completed. Contracturally, the units are to be delivered in groups on
specific dates (7 total). Each unit's logic is virturally the same with a
few minor exceptions. I have included several text columns to break down
Area, Type, Option, Variation, Unit No., Group, and Construction Sequence.
My schedule shows 10 groups comprised of 74 units. The early finish dates
are 6-12 months ahead of the contractural completions dates. Naturally, I
want to finish by the early finish dates and naturally, I want to show the
owner the contract completion dates. I have been including an activity
called "Administrative Closeout" linked between the next to the last
scheduled activity and the last scheduled activity of each unit, with a
duration equal to the finish slack between the early finish and the
contractural (late) finish date of that unit. The problem is when I do this,
almost every activity in each unit's logic becomes critical path.
I know this isn't an uncommon problem, so I'm looking for suggestions.
ccgsuper