Hello,
I have got an issue about actual work and duration. Hopefully someone
has got a solution or a good work-arround for me. I have also seen
this problem in this newsgroup, dated last year, but I could not react
to that one.
The issue is:
I have entered a task in MS Project, assigned a resource to it,
entered the duration and the work. The Team Member, assigned to this
task, has entered actual work through his timesheet on Project Web
Access. Actual work was rightly updated into my project plan.
Everything was allright till I changed the duration.
Changing the duration changes the actual work. For example:
Duration 10 days
Work 40 hours
Actual Work 20 hours
Changing duration to 5 days
Fixed work, so a change of Units.
BUT Actual Work also changes!! Actual work is realized and should not
be changed.
Does someone has got the same problem and does someone know a
solution?
Thanks, best regards,
Jeroen
I have got an issue about actual work and duration. Hopefully someone
has got a solution or a good work-arround for me. I have also seen
this problem in this newsgroup, dated last year, but I could not react
to that one.
The issue is:
I have entered a task in MS Project, assigned a resource to it,
entered the duration and the work. The Team Member, assigned to this
task, has entered actual work through his timesheet on Project Web
Access. Actual work was rightly updated into my project plan.
Everything was allright till I changed the duration.
Changing the duration changes the actual work. For example:
Duration 10 days
Work 40 hours
Actual Work 20 hours
Changing duration to 5 days
Fixed work, so a change of Units.
BUT Actual Work also changes!! Actual work is realized and should not
be changed.
Does someone has got the same problem and does someone know a
solution?
Thanks, best regards,
Jeroen