D
deb harvey
Can anyone help a v raw project beginner to record actual
work times and actual start dates of a project where
resources are doing 1 -6hrs work a day on one or more
tasks. Everytime i do it, the duration changes or the
start date or it tells me that i still have work to
do..Arrg i am in a real muddle. My trainer had only used
98 and the complexities of 2003 really stumped even him
so it wasn't adequate level of training which didn't help.
All help much appreciated
DH
work times and actual start dates of a project where
resources are doing 1 -6hrs work a day on one or more
tasks. Everytime i do it, the duration changes or the
start date or it tells me that i still have work to
do..Arrg i am in a real muddle. My trainer had only used
98 and the complexities of 2003 really stumped even him
so it wasn't adequate level of training which didn't help.
All help much appreciated
DH