I've investigated further and would like to detail my findings, please
ignore my previous post.
Scenario:
I have a task with assignments, I give the assignments a TimeScaleValue
for ActualWork which sets the Start and End dates for the task.
I change the End Date(to finish later) for the task and the Actual Work
assignment is split across the newly added days!
Alternatively:
Same scenario but I change the Start Date(to start earlier) for the
task, this causes the Actual Work assignment to be moved to the new
start date!
I would understand that it do this for Work, but why does it change the
Actual Work ?! I would have thought that actual Work is fixed and thus
imovable.
Any help is much appreciated.
thanks,
John
ignore my previous post.
Scenario:
I have a task with assignments, I give the assignments a TimeScaleValue
for ActualWork which sets the Start and End dates for the task.
I change the End Date(to finish later) for the task and the Actual Work
assignment is split across the newly added days!
Alternatively:
Same scenario but I change the Start Date(to start earlier) for the
task, this causes the Actual Work assignment to be moved to the new
start date!
I would understand that it do this for Work, but why does it change the
Actual Work ?! I would have thought that actual Work is fixed and thus
imovable.
Any help is much appreciated.
thanks,
John