J
jay
Desktop: MS Project Professional 2002 SP-1
Server: MS Project Server 2003 SP-1
Both the Resource Usage view and the Resource Usage report allow one to
determine total actual work by Resource (by time period) if and only if all
of the projects that the Resource(s) have been assigned to have been
identified and opened prior to execution of either the view or the report.
For a project manager with 6-10 open projects, the above process is
inefficient. Also, excluding a project could yield incomplete information.
Is there a more efficient way to determine this information with the base
product?
Thanks in advance for your feedback.
Server: MS Project Server 2003 SP-1
Both the Resource Usage view and the Resource Usage report allow one to
determine total actual work by Resource (by time period) if and only if all
of the projects that the Resource(s) have been assigned to have been
identified and opened prior to execution of either the view or the report.
For a project manager with 6-10 open projects, the above process is
inefficient. Also, excluding a project could yield incomplete information.
Is there a more efficient way to determine this information with the base
product?
Thanks in advance for your feedback.