Actual work changes duration

V

Vazabe

Have a task that is Fixed work where Duration=1h, Work=1h with a resource
assigned 100%.

When an actual of 0,5h is entered and Remaining Work is set to Oh then
Duration is set to 8h. Why is this? Should it not be 0,5h?
 
G

Gérard Ducouret

Hi Vazabe,

The issue comes from the timescale of the Timesheet in PWA : the smallest
unit is the day, so the Actual Work (0,5h) is spread on the entire day ;-(

Nevertheless, you could, if your are enough patient ;-( , change the
timescale in the Task Usage view of Project Pro (hours and 15mn for example)
and correct the Actual Work distribution. then Collaborate / Publish /
Republish Assignments. / Overwrite actual work entered by resources



Gérard Ducouret
 