actual work changes duration

O

Olivia

Post on Sept2006 Gérard Ducouret wrote
"The issue comes from the timescale of the Timesheet in PWA : the smallest
unit is the day, so the Actual Work (0,5h) is spread on the entire day ;-(

Nevertheless, you could, if your are enough patient ;-( , change the
timescale in the Task Usage view of Project Pro (hours and 15mn for example)
and correct the Actual Work distribution. then Collaborate / Publish /
Republish Assignments. / Overwrite actual work entered by resources "
Is this a known bug? does it mean if actual hours less than 8, duration will
always change and schedule will never calculate right? If I do what is
suggested in the post, does it mean every time I update my project plan, I
have to correct my plan manually? Thanks in advance for any help!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top