R
Rod C
I guess I misunderstand how to record actuals in a plan. We are using MS
Project 2003.
I have a task of duration 10 days with 40 hours scheduled effort.
The task completes in 5 days and takes 35 hours actual work.
I want to be able to record the task as 100% complete after 5 days. I do not
seem to be able to get the result I need in the %complete nor the %work
complete.
As an adjunct, I have another task (same project) of 20 days duration and
100 hours estimated effort (work). After 10 days the resource has spent 40
hours and the task is 75% complete (not 40% as 40/100 would indicate, and not
50% as the duration estimate would indicate). How would one record this
actuality?
Project 2003.
I have a task of duration 10 days with 40 hours scheduled effort.
The task completes in 5 days and takes 35 hours actual work.
I want to be able to record the task as 100% complete after 5 days. I do not
seem to be able to get the result I need in the %complete nor the %work
complete.
As an adjunct, I have another task (same project) of 20 days duration and
100 hours estimated effort (work). After 10 days the resource has spent 40
hours and the task is 75% complete (not 40% as 40/100 would indicate, and not
50% as the duration estimate would indicate). How would one record this
actuality?