Actual work display in 2 different user defined views

U

Umamahesh

Hi,

Created a view with View Type as Project seleting fields Baseline Start,
Baseline Finish, Actual Start, Actual Finish, Baseline Work and Actual Work.

With the same field selection, created another view of View Type Project
Center.

When I launch the view under Projects interface clicking Project Name, first
view is displaying proper Actual Work. In the same interface when I select
the second view from Choose View drop down, second view is displaying Actual
Work as 0 at project level.

Kindly clarify, if anything need to do.

Regards,
P.Umamahesh
 
U

Umamahesh

As per the details it is Office Project Server 2003. No other details are
mentioned.
 
U

Umamahesh

I am trying to get the version of the software.
Meanwhile do you require the product id to propose the solution?
 
U

Umamahesh

The version details are as follows:

Microsoft Office Project Server 2003
Version: 11.0.5614.0
--
 