Hi
I am using PS2007, SP1
I created an OALP view able to display both "Work" & "Actual Work" for the
different tasks a resource is in charge with.
But current OLAP displays values once tasks updates have been "re-published".
Is there any means to display "Actual Work" before tasks updates have been
submitted/approved/published?
My need is the following:
- user1 is supposed to works on 5 tasks
- user1 updates tasks progress on a daily and/or weekly basis according to
tasks progress
=>Here I'd like to provide user1 with a report view#1 per day & week to
display "Actual Work" he entered so far (as well as "Work" that is planned)
-then user1 runs report view#1 to enable him/her to check whether he/she
indeed entered right quantity of work for the said week.
Actually I'd like to obtain similar check view as provided within timesheet:
"Actual Work" vs planned "Work" but with avoiding using timesheet for time
collection.
thanks for your help
jpa
I am using PS2007, SP1
I created an OALP view able to display both "Work" & "Actual Work" for the
different tasks a resource is in charge with.
But current OLAP displays values once tasks updates have been "re-published".
Is there any means to display "Actual Work" before tasks updates have been
submitted/approved/published?
My need is the following:
- user1 is supposed to works on 5 tasks
- user1 updates tasks progress on a daily and/or weekly basis according to
tasks progress
=>Here I'd like to provide user1 with a report view#1 per day & week to
display "Actual Work" he entered so far (as well as "Work" that is planned)
-then user1 runs report view#1 to enable him/her to check whether he/she
indeed entered right quantity of work for the said week.
Actually I'd like to obtain similar check view as provided within timesheet:
"Actual Work" vs planned "Work" but with avoiding using timesheet for time
collection.
thanks for your help
jpa