Actual Work Doesn't Match

J

Jan

I created an analyzer view that is displaying scheduled, availability and
actual work by resource and project. I also needed to drill down to the task
level so exported the Adjusted Actuals data for the resources and projects
being reviewed. However Analyzer totals don't matrch Adjusted Actual total.

What is causing this?
 
M

Marc Soester [MVP]

Hi Jan,

the first thing that spings into my mind is "have you re-build the OLAP
cubes?" If you update a project and then check out the data analyser view
straight afterwards, the change will not be reflected. It will only be
reflected after you have re-build the cube. Generally this is done on a daily
basis.
Hope this make sense.
 