Actual work done in terms of material resource through statusing update in PSI

I

invincible

Hello Friends ,

How can i report actual work done in terms of material resource
through statusing update in PSI(Project Server Interface)..

I am able to successfully do that in Project Professional 2007 ..

PSI allows us to make actual work updates in terms of Hours,minutes or
days but not in terms of material units consumed..

e.g. How can i enter that 135.5 bags of cement were consumed (actual
work done )for a particular assignment of 150 bags through PSI ??

Thanks in advance..
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top