J
Jim Puls
I have a task in a project which is expected to take 4 hours over a
five day period, so the duration is five days. I update the actual
work during this period, from one to four hours. When the task is
complete, I set the % complete to 100% for the task, and then the
actual work jumps to 40 hours (8 hours per day times 5 days).
How should I set up the task so that 100% is 4 hours and the duration
is 5 days?
Thanks!
- Jim
five day period, so the duration is five days. I update the actual
work during this period, from one to four hours. When the task is
complete, I set the % complete to 100% for the task, and then the
actual work jumps to 40 hours (8 hours per day times 5 days).
How should I set up the task so that 100% is 4 hours and the duration
is 5 days?
Thanks!
- Jim