Actual work entered by resources in PWA.

N

Niki

Actuals entered in PWA are replaced with the actual work values in
MSProject2003 before actuals entered in PWA has been published.

How can I get back actuals entered in personal timesheets in PWA?

Thanks, Niki
 
D

Dale Howard [MVP]

Niki --

By chance, did you open the project, click Collaborate - Publish - Republish
Assignements, select the "Overwrite actual work entered by resources"
option, and then click OK? If your team members had entered actuals in
their PWA timesheets, but you had not updated the actuals into the Microsoft
Project plan, then the process of republishing the assignments detailed in
the first sentence above will wipe out the actuals in each team member's
timesheet. I know of no way to restore the original actuals in the PWA
timesheets. Sorry. Hope this helps.
 