T
Tim Garvey
I have a task called, of all things, "Project Management." I've basically
set up my tasks so that I spend 27 hrs per week on Project management, 5
hours a week on HR management, and 8 hours a week on MS Project Plan
Maintenance between now and August of 2010.
For the weeks of 1/24 and 1/31, whatever hours I schedule (enter in the
"work" cell in the Resource Usage View) for the Project Management task also
appear in the "actual" cell. So I have 27 hours scheduled and actual for
next week and the week after. This doesn't happen for this task for any of
the subsequent weeks going out to August of 2010.
The tasks are not closed (complete). Some are Fixed work and some are
fixed duration.
Any help would be greatly appreciated.
set up my tasks so that I spend 27 hrs per week on Project management, 5
hours a week on HR management, and 8 hours a week on MS Project Plan
Maintenance between now and August of 2010.
For the weeks of 1/24 and 1/31, whatever hours I schedule (enter in the
"work" cell in the Resource Usage View) for the Project Management task also
appear in the "actual" cell. So I have 27 hours scheduled and actual for
next week and the week after. This doesn't happen for this task for any of
the subsequent weeks going out to August of 2010.
The tasks are not closed (complete). Some are Fixed work and some are
fixed duration.
Any help would be greatly appreciated.