In trying to create some new views for the Project Center, the Actual Work
field only displays 0h for all projects.

All attempts to add the Actual Work field to a view result in all zeros.
Other fields, like Work, % Work Complete, etc. are all fine.

To complicate matters, an older view which uses Actual Work DOES have all
the appropriate values in it.

Any ideas?????

Perhaps on a related front: If I added say, Enterprise Project Number 1 to
a view, the column header might come up and read: Enterprise Project Text 25.
This is bizarre and inexplicable behavior to me.
 