J
JIM
Hi there!
We've a serious issues with Actual Work in future time-periods...
Our setting is MS Project Server 2007, SP2, April CUP. The "Actual Work"
lock is activated (the option that should protect the Actual Work). Actual
Work is reported within "My Tasks".
We've double checked the situation, and the reported Actual Work. We've also
checked the transaction protocol of "My Tasks". The users have definetly
sumbittet in the past. A rule has automatically accepted this data and
approved the transfer to the project plan. However, now some of the Actual
Work is shown in future...
Any ideas? Is this a known issue?
Thx,
Jim
We've a serious issues with Actual Work in future time-periods...
Our setting is MS Project Server 2007, SP2, April CUP. The "Actual Work"
lock is activated (the option that should protect the Actual Work). Actual
Work is reported within "My Tasks".
We've double checked the situation, and the reported Actual Work. We've also
checked the transaction protocol of "My Tasks". The users have definetly
sumbittet in the past. A rule has automatically accepted this data and
approved the transfer to the project plan. However, now some of the Actual
Work is shown in future...
Any ideas? Is this a known issue?
Thx,
Jim