Actual work in future timesheets

J

Jose Antonio

Hi,

We know some people have this problem: actual work appears in future dates
in timesheets.

We are evaluating the option to create a tool to automatically delete this
entries in the future. We will give it for free to the community.

Just want to know who is interested on it.

Regards,
Jose
 
M

milrock

What patch level is Project Server at? Does the implementation have
Adminstrative time categories that are non-working? Also, are updates
restricted to PWA only in the Task Settings and Display section of PWA
(PMs could have made a task completing in the future 100% complete
which would populate a users timesheet in the future).

There are several reasons why this could happen. If you answer the
above questions it will be a little easier to diagnose the problem
you're experiencing.

S
 
J

Jose Antonio

Thank you.

It was a well known bug. I appeared after SP2 and was corrected later but
now we must delete the incorrect data.

Regards
Jose.
 