Nancy
I have created a view in Portfolio Analyzer to show each resource's actual
work per day per project however I am getting results like 32 hours for one
day for one person - which is obviously wrong. I've updated the OLAP cube
several times but I get the same result. I've also filtered the view down to
just that one day and the one person with 32 hours but the results never
change. I've checked the actual time for this resource in PWA and see she
only recorded 16 hours for that particular day. Any thoughts or suggestions?
Thanks!
work per day per project however I am getting results like 32 hours for one
day for one person - which is obviously wrong. I've updated the OLAP cube
several times but I get the same result. I've also filtered the view down to
just that one day and the one person with 32 hours but the results never
change. I've checked the actual time for this resource in PWA and see she
only recorded 16 hours for that particular day. Any thoughts or suggestions?
Thanks!