Hello Friends ,
How can i report actual work done in terms of material resource
through statusing update in PSI(Project Server Interface)..
I am able to successfully do that in Project Professional 2007 ..
PSI allows us to make actual work updates in terms of Hours,minutes
or
days but not in terms of material units consumed..
e.g. How can i enter that 135.5 bags of cement were consumed (actual
work done )for a particular assignment of 150 bags through PSI ??
Thanks in advance..