I
Ingrid Weng
I found that one of the task's actual work in Project Professional is not
equal to the data inputed from PWA.
I retrieve the data inputed by resource and brek it into daily record from
MSP_WEB_WORK, there is no data on 12/1, but the Project Professional shows
data on that day by using Resource Usage view, and, the actual work is also
mismatch.
This issue occured after applying 'Sync to Protected Actuals'.
I found KB838009 - Actual Work submitted by a resource in Project Web Access
appears incorrect after you synchronize in Project 2003
But both my Project or Proejct Server 2003 applied SP1 already.
Any idea what else I should do? Please help! Thanks in advanced.
equal to the data inputed from PWA.
I retrieve the data inputed by resource and brek it into daily record from
MSP_WEB_WORK, there is no data on 12/1, but the Project Professional shows
data on that day by using Resource Usage view, and, the actual work is also
mismatch.
This issue occured after applying 'Sync to Protected Actuals'.
I found KB838009 - Actual Work submitted by a resource in Project Web Access
appears incorrect after you synchronize in Project 2003
But both my Project or Proejct Server 2003 applied SP1 already.
Any idea what else I should do? Please help! Thanks in advanced.