B
Barbara G
Hi,
My organization uses both Project Professional 2007 and Project Server 2007.
The resources actual work is protected. After they import their timesheet
through Project Web Access, the project manager accepts the request but the
project doesn't reflect the actual work in the plan. I'm still in the process
of testing SP1 so that hasn't been installed yet. The resources don't upate
the remaining work through PWA. Only the project managers update the
remaining work. Does anyone know why these actual hours aren't visible in
this project? Any help is greatly appreciated.
Thanks,
My organization uses both Project Professional 2007 and Project Server 2007.
The resources actual work is protected. After they import their timesheet
through Project Web Access, the project manager accepts the request but the
project doesn't reflect the actual work in the plan. I'm still in the process
of testing SP1 so that hasn't been installed yet. The resources don't upate
the remaining work through PWA. Only the project managers update the
remaining work. Does anyone know why these actual hours aren't visible in
this project? Any help is greatly appreciated.
Thanks,