E
EJSett
After actuals were entered through My Tasks in PWA, approved and published
they were still not visible through the resource assignment view or the OLAP
reports. The information was available and correct when viewing it in the
resource usage view in Project Professional. We are on MS Project Server 2007.
Has anyone ever had this problem or know of any reasons why this would happen?
they were still not visible through the resource assignment view or the OLAP
reports. The information was available and correct when viewing it in the
resource usage view in Project Professional. We are on MS Project Server 2007.
Has anyone ever had this problem or know of any reasons why this would happen?