Noynoy
Hi All,
We are seeing inconsistencies with our PWA views and Project PRO
views. In the View Resource Assignments (Timesheet Format), the actual
work is not showing up even if the Resource Usage View in Project PRO
contains information of the actual work done. Is there anything we
should be doing to make the actual work values show up in the View
Resource Assignments in PWA?
Our setup is MS Project Server 2003 SP3 running on MS SQL 2005. MS
Project PRO is on the latest service pack.
Thanks in advance.
rgds,
Noynoy
We are seeing inconsistencies with our PWA views and Project PRO
views. In the View Resource Assignments (Timesheet Format), the actual
work is not showing up even if the Resource Usage View in Project PRO
contains information of the actual work done. Is there anything we
should be doing to make the actual work values show up in the View
Resource Assignments in PWA?
Our setup is MS Project Server 2003 SP3 running on MS SQL 2005. MS
Project PRO is on the latest service pack.
Thanks in advance.
rgds,
Noynoy