Actual Work not showing in View Resource Assignments Timesheet Format

N

Noynoy

Hi All,

We are seeing inconsistencies with our PWA views and Project PRO
views. In the View Resource Assignments (Timesheet Format), the actual
work is not showing up even if the Resource Usage View in Project PRO
contains information of the actual work done. Is there anything we
should be doing to make the actual work values show up in the View
Resource Assignments in PWA?

Our setup is MS Project Server 2003 SP3 running on MS SQL 2005. MS
Project PRO is on the latest service pack.

Thanks in advance.

rgds,

Noynoy
 
P

piyusha.manish

Hi All,

We are seeing inconsistencies with our PWA views and Project PRO
views. In the View Resource Assignments (Timesheet Format), the actual
work is not showing up even if the Resource Usage View in Project PRO
contains information of the actual work done. Is there anything we
should be doing to make the actual work values show up in the View
Resource Assignments in PWA?

Our setup is MS Project Server 2003 SP3 running on MS SQL 2005. MS
Project PRO is on the latest service pack.

Thanks in advance.

rgds,

Noynoy

Thats a known bug of microsoft.It has been fixed in SP2
Piyusha
 
P

piyusha.manish

Hi All,

We are seeing inconsistencies with our PWA views and Project PRO
views. In the View Resource Assignments (Timesheet Format), the actual
work is not showing up even if the Resource Usage View in Project PRO
contains information of the actual work done. Is there anything we
should be doing to make the actual work values show up in the View
Resource Assignments in PWA?

Our setup is MS Project Server 2003 SP3 running on MS SQL 2005. MS
Project PRO is on the latest service pack.

Thanks in advance.

rgds,

Noynoy

Move to Project serevr 2007 with sp2.your pb will be resolved
Piyusha
 
N

Noynoy

Thats a known bug of microsoft.It has been fixed in SP2
Piyusha- Hide quoted text -

- Show quoted text -

Hi Piyusha,

Thanks for the tip. Do you have any documentation whatsoever about
this bug?

rgds,

Noynoy
 
D

Dale Howard [MVP]

Piyusha --

The person who asked the question is using Project Server 2003. And
Microsoft has not yet released SP2 for Project Server 2007.




Hi All,

We are seeing inconsistencies with our PWA views and Project PRO
views. In the View Resource Assignments (Timesheet Format), the actual
work is not showing up even if the Resource Usage View in Project PRO
contains information of the actual work done. Is there anything we
should be doing to make the actual work values show up in the View
Resource Assignments in PWA?

Our setup is MS Project Server 2003 SP3 running on MS SQL 2005. MS
Project PRO is on the latest service pack.

Thanks in advance.

rgds,

Noynoy

Move to Project serevr 2007 with sp2.your pb will be resolved
Piyusha
 
N

Noynoy

Piyusha --

The person who asked the question is using Project Server 2003.  And
Microsoft has not yet released SP2 for Project Server 2007.









Move to Project serevr 2007 with sp2.your pb will be resolved
Piyusha- Hide quoted text -

- Show quoted text -

Hi,

Can anyone confirm if this is a bug in PS2003?

rgds,

Noynoy
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top