W
Wil
In a timesheet view it seems that actual work of "tasks" from an
adminstrative project is not shown in the sheet column Actual Work but in
Remaining Work. In the same view the % work complete is 0. The same timesheet
view shows the values of tasks in "normal" projects in the right columns.
I checked with project professional and an olap cube. Both show actuals in
administrative projects the way they should.
Has anyone seen this phenomenon and an idea of the cause?
adminstrative project is not shown in the sheet column Actual Work but in
Remaining Work. In the same view the % work complete is 0. The same timesheet
view shows the values of tasks in "normal" projects in the right columns.
I checked with project professional and an olap cube. Both show actuals in
administrative projects the way they should.
Has anyone seen this phenomenon and an idea of the cause?