S
Stefan van Aalst
Hi
We experience the following:
When on Project Server In Resource Usage we see:
- which tasks are worked upon and: work, actual work, etc
- of non-opened projects: only work (not actual work, not actual cost, etc)
When I do a shared resource thing off-line, I see in Resource Usage:
- which tasks are worked upon and: work, actual work, etc
- of non-opened projects: work, actual work, etc
Is there a setting not okay in the server or is something else the reason
why for non-opened projects Actual Work is empty in MS-project when connected
to project server?
I would expect, more than in the off-line thing, to see all actuals even
when the project is not opened.
Much obliged
Stefanb
We experience the following:
When on Project Server In Resource Usage we see:
- which tasks are worked upon and: work, actual work, etc
- of non-opened projects: only work (not actual work, not actual cost, etc)
When I do a shared resource thing off-line, I see in Resource Usage:
- which tasks are worked upon and: work, actual work, etc
- of non-opened projects: work, actual work, etc
Is there a setting not okay in the server or is something else the reason
why for non-opened projects Actual Work is empty in MS-project when connected
to project server?
I would expect, more than in the off-line thing, to see all actuals even
when the project is not opened.
Much obliged
Stefanb