Actual Work & OT Work changes in My Timesheet

R

reza

Hi All,

Since there aren't any comments so i re post it back.

I'm using MS Pro 2007, PS 2007, SP1 & Dec Cum.
I have scenario in below:
For example I open project and update Task 1 for March 23 using Task Usage
view, i enter value for task 1 with Actual work 12 hrs & actual overtime work
4 hrs, save & publish it.
Using timephase view, i go to my task, in March 23 coloum for task 1, i can
see 12 hrs with 4 hrs in actual overtime work coloum.
Then i go to my timesheet, in there i see, the values in standard row become
12 hrs and in overtime 3 hrs...so total for march 23 is 14 hrs. I believe the
right one is 12 hrs.
Also i tried in Enterprise Project, i enter values for task 2 is 8 hrs in
Actual
Overtime Work and in Timesheet will be standard 12 hrs and overtime 12
hrs,so total for that day become 24 hrs.
anyone know about this problem???

Thanks
 