Actual Work protected & Actual work not matching

  • Thread starter Needhi rajan John williams
  • Start date
N

Needhi rajan John williams

Hi all,

I am using project Server 2003. After my team members enter the actual work in PWA.

I find the differences in the Actual Work Protected & actual work in few of the tasks.

Can anyone tell me what could be the reason.

Regards
Needhi rajan PMP

EggHeadCafe.com - .NET Developer Portal of Choice
http://www.eggheadcafe.com
 
M

Mark Everett | PMP

Hi all,

I am using project Server 2003. After my team members enter the actual work in PWA.

I find the differences in the Actual Work Protected & actual work in few of the tasks.

Can anyone tell me what could be the reason.

Regards
Needhi rajan PMP

EggHeadCafe.com - .NET Developer Portal of Choicehttp://www.eggheadcafe.com

The most obvious reason is that the project managers are editing the
actual work in Project Professional, especially since it only appears
in a few tasks.

Hope this helps,

Mark Everett | PMP
www.quantumpm.com
 
S

Sandeep

Actual Work is the overall work submitted on the tasks but not necessarily all hours approved by manager

vs Actual Work Protected are approved actual hours

EggHeadCafe.com - .NET Developer Portal of Choice
http://www.eggheadcafe.com
 
N

Needhi Rajan

Thanks Sandeep & Mark,

Another issue is, In Project pro Actual work protected has 4 hrs , but for
the same task, time period, the data is empty in PWA.

Actually I wanted to adjust the data for the time period in PWA using "
ADJUST ACTUALS".

So I just want to know "IS there any way to adjust the "actual Work
protected" data in project Pro itself?

Thanks
Needhi rajan PMP
 