J
jlg
Greetings,
We are a Project Server 2003 environment running managed time periods.
My understanding is:
Actual Work is the overall work submitted on the tasks but not
necessarily all hours approved by manager vs Actual Work Protected are
the approved actual hours.
If the above is true, when would actual hours ever be less then actual
work protected for a given day?
I see that scenario in our OLAP cube and in the project plan in MS
Project.
Thanks for any insight you can provide,
jlg
We are a Project Server 2003 environment running managed time periods.
My understanding is:
Actual Work is the overall work submitted on the tasks but not
necessarily all hours approved by manager vs Actual Work Protected are
the approved actual hours.
If the above is true, when would actual hours ever be less then actual
work protected for a given day?
I see that scenario in our OLAP cube and in the project plan in MS
Project.
Thanks for any insight you can provide,
jlg