Actual Work Protected et Overtime Work Protected fields

R

Robert

Hello,

What is the use of the new fields that we can find in the Resource Usage
view of Project 2003:
Actual Work Protected and Overtime Work Protected.

Thanks,

Gérard Ducouret
 
D

Dale Howard [MVP]

Robert (Gerard) --

They are used with managed time periods. When a managed time period if
closed, an Actual Work and Actual Overtime Work values entered during that
time period are protected from change. In essence, they are locked.
Managed time periods also prevents people from entering time in future time
periods as well. Hope this helps.
 