Johnnie
I have some tasks when updated with actual work will add zeroes for actual
work in the future. For example: Task A is schedule to start 5/14 based on
predecessors and is scheduled for 5 hours (fixed work). However the work
actually starts on 5/8 and resource enters 2 hours in PWA. When the schedule
is updated from PWA, the actual work is accurately transferred and remaining
work is allocated to 5/14. However, between 5/8 and 5/14, the schedule show
0 hrs work (which is correct) and 0 hrs actual work (shouldn't not show any
numbers at all). If the PM tries to adjust, i.e., move the remaing work in,
project will now allow this to happen. I have checked the work settings
against others schedules any they are the same.
Any ides what may be causing this? Thanks for your help.
Johnnie
work in the future. For example: Task A is schedule to start 5/14 based on
predecessors and is scheduled for 5 hours (fixed work). However the work
actually starts on 5/8 and resource enters 2 hours in PWA. When the schedule
is updated from PWA, the actual work is accurately transferred and remaining
work is allocated to 5/14. However, between 5/8 and 5/14, the schedule show
0 hrs work (which is correct) and 0 hrs actual work (shouldn't not show any
numbers at all). If the PM tries to adjust, i.e., move the remaing work in,
project will now allow this to happen. I have checked the work settings
against others schedules any they are the same.
Any ides what may be causing this? Thanks for your help.
Johnnie