D
Doug Schurman
Project Server 2003
We are trying develop a report to show us the time entered in a given time
frame (usually last week) and whether or not that time is still within the
baseline for the given assignment. For example if Joe is assigned a task and
is baselined 10 hours, had worked 5 hours prior to last week and then worked
3 more these 3 hours would be “on budgetâ€. If he had already worked 10 or
more prior to last week these 3 hours would all be “over budgetâ€.
All of this raw data is displayed on the timesheet entry tab that would be
needed. We are having a hard time getting this data to be available ether in
Portfolio analyzer or in a custom SQL query. What do we need to be able to do
to pull assignments by person, show total baseline, total timesheet work
entered and show timesheet work entered for a recent period (like last week)?
Thanks
Doug
We are trying develop a report to show us the time entered in a given time
frame (usually last week) and whether or not that time is still within the
baseline for the given assignment. For example if Joe is assigned a task and
is baselined 10 hours, had worked 5 hours prior to last week and then worked
3 more these 3 hours would be “on budgetâ€. If he had already worked 10 or
more prior to last week these 3 hours would all be “over budgetâ€.
All of this raw data is displayed on the timesheet entry tab that would be
needed. We are having a hard time getting this data to be available ether in
Portfolio analyzer or in a custom SQL query. What do we need to be able to do
to pull assignments by person, show total baseline, total timesheet work
entered and show timesheet work entered for a recent period (like last week)?
Thanks
Doug