M
MAPretty
I am revising my workplan assignments. I have some tasks that have some work
done by a resource. When I add another resource to that task, and enter an
amount of hours for Work, Project is putting some of those hours in the
Actual Work field, and some in the Work field for that assignment. In my
opinion, it should never put anything in the Actual Work field.
I am using PWA to enter actual work using the Timesheet feature.
I'm using MS Project Server Prof. 2003, SP1.
Does anyone know why it's doing this?
done by a resource. When I add another resource to that task, and enter an
amount of hours for Work, Project is putting some of those hours in the
Actual Work field, and some in the Work field for that assignment. In my
opinion, it should never put anything in the Actual Work field.
I am using PWA to enter actual work using the Timesheet feature.
I'm using MS Project Server Prof. 2003, SP1.
Does anyone know why it's doing this?