Actual Work values all equal zero in Project Center in Web Access

P

ProjectAnalyst

Hi, I created a new view with Actual Work in it for Project Center. (Project
Server 2002 with latest MDAC and SP on server and clients).

After saving the view, closing and opening Project and Web Access, I open up
Web Access that the values in the Actual Work column are all zero.

I have an older view that shows Actual Work in the Project Center views just
fine, and can't think what I've missed.

ideas?
 
G

Gérard Ducouret

Hello ProjectAnalyst,

Did you published all the projects after you created these new views ?
Collaborate / Publish / All Information

Gérard Ducouret
 
P

ProjectAnalyst

Not all of them just a couple I wanted to see data for. There are about
100...do I need to do them ALL?!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top