R
Robert
Hello,
What is the difference between "Actual Work" and "Actual Work Billable" ?
In the timesheets, resources are not using Actual Work billable. They enter
time only on Actual Work.
Timesheets have been validated, but the actuals are not imported in Project
Pro.
I created two Data Analysis views:
- 1st based on MSP_Project_Timesheet cube, which displays the Actual Work.
- 2nd based on EPM Timesheet cube, which displays the Actual Work Billable
(we don't have other choice)
1st pivot table (Actual Work) displays 0 values on months where there are
some (expected) actuals
2nd pivot table (Actual Work Billable) displays the right values where there
are some actuals.
Thanks for your help
What is the difference between "Actual Work" and "Actual Work Billable" ?
In the timesheets, resources are not using Actual Work billable. They enter
time only on Actual Work.
Timesheets have been validated, but the actuals are not imported in Project
Pro.
I created two Data Analysis views:
- 1st based on MSP_Project_Timesheet cube, which displays the Actual Work.
- 2nd based on EPM Timesheet cube, which displays the Actual Work Billable
(we don't have other choice)
1st pivot table (Actual Work) displays 0 values on months where there are
some (expected) actuals
2nd pivot table (Actual Work Billable) displays the right values where there
are some actuals.
Thanks for your help