L
Laura
hello, probably my question will be strange for intensive user of project
server 2007..sorry but i'm still kinda new of it.
I have some problem in managing actual work insert from my team member.
They submit their timesheets to me weekly. they import actual work to my
task page and then submit also this page.
then I accept their actual work on the project but sometimes it could
happend that some of their actual work is different from their
timesheet...and they didin't change it on my task page.
for example my team member insert on a task of a project in TIMESHEET
tuesday 6h
wednesday 4h
then they import and sumbit on MY TASK page
when i view their impact on the project then I saw:
monday 1,38h
tuesday 5,62h
wednesday 0h
why does project do this?
someboby can help me?
thank you very very much!
server 2007..sorry but i'm still kinda new of it.
I have some problem in managing actual work insert from my team member.
They submit their timesheets to me weekly. they import actual work to my
task page and then submit also this page.
then I accept their actual work on the project but sometimes it could
happend that some of their actual work is different from their
timesheet...and they didin't change it on my task page.
for example my team member insert on a task of a project in TIMESHEET
tuesday 6h
wednesday 4h
then they import and sumbit on MY TASK page
when i view their impact on the project then I saw:
monday 1,38h
tuesday 5,62h
wednesday 0h
why does project do this?
someboby can help me?
thank you very very much!