A
Annerike Hendriks
I enter our actual hours worked on the resource usage sheet in Project 2002.
When I insert a new resource to a task which has already Actual Work booked from other resources, sometimes Project automatically gives the new resource an ammount of Actual Work instead that the Actual Work for the new resource is "0 hours". The tasktype is "Fixed Units" or "Fixed Work" en the "% complete = 100"
This means that the Actual Work in Project is not always the same ammount of hours that I have entered on the resource usage sheet in Project
Does someone knows a solution
Annerik
When I insert a new resource to a task which has already Actual Work booked from other resources, sometimes Project automatically gives the new resource an ammount of Actual Work instead that the Actual Work for the new resource is "0 hours". The tasktype is "Fixed Units" or "Fixed Work" en the "% complete = 100"
This means that the Actual Work in Project is not always the same ammount of hours that I have entered on the resource usage sheet in Project
Does someone knows a solution
Annerik