Actual Work

A

Annerike Hendriks

I enter our actual hours worked on the resource usage sheet in Project 2002.
When I insert a new resource to a task which has already Actual Work booked from other resources, sometimes Project automatically gives the new resource an ammount of Actual Work instead that the Actual Work for the new resource is "0 hours". The tasktype is "Fixed Units" or "Fixed Work" en the "% complete = 100"
This means that the Actual Work in Project is not always the same ammount of hours that I have entered on the resource usage sheet in Project

Does someone knows a solution

Annerik
 
J

JulieS

Annerike,
I believe the problem you are seeing is because the task
is 100% complete. When you add resources to tasks that
are complete, project assumes that the added resource
also had actual work equal to scheduled work.

Julie
-----Original Message-----
I enter our actual hours worked on the resource usage sheet in Project 2002.
When I insert a new resource to a task which has already
Actual Work booked from other resources, sometimes
Project automatically gives the new resource an ammount
of Actual Work instead that the Actual Work for the new
resource is "0 hours". The tasktype is "Fixed Units"
or "Fixed Work" en the "% complete = 100".
This means that the Actual Work in Project is not always
the same ammount of hours that I have entered on the
resource usage sheet in Project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top