H
Holmin
Hello Everyone,
I'm new to Project and I'm using Project 2003 Pro.
I have a problem that I don't know how to solve. I have task that is shared
by two resources at 50%. But in reality it could be that resource 1 works 5
hours a specific day and resource 2 works just 3 hours that same day instead
of both working 4 hours each. The fifth hour that day for resource 1 is not
overtime since he works 8 hours a day, but is just assigned for 50% at the
task due to other work assignments (not in Project). How do I record this
actual work in the resource usage view?
When I try to put in an extra hour for resource 1 it get shifted to next day
instead and that's not what I want at all.
Any suggestions, anyone?
Sincerely,
Holmin
I'm new to Project and I'm using Project 2003 Pro.
I have a problem that I don't know how to solve. I have task that is shared
by two resources at 50%. But in reality it could be that resource 1 works 5
hours a specific day and resource 2 works just 3 hours that same day instead
of both working 4 hours each. The fifth hour that day for resource 1 is not
overtime since he works 8 hours a day, but is just assigned for 50% at the
task due to other work assignments (not in Project). How do I record this
actual work in the resource usage view?
When I try to put in an extra hour for resource 1 it get shifted to next day
instead and that's not what I want at all.
Any suggestions, anyone?
Sincerely,
Holmin