Actualize customized fields?

M

Maik Richter

Hi guys,



I created a Masterproject and added many Single-projects. The Masterproject

is connected with the Ressource Pool. I added a custom field (=Work) to the

Gantt Chart view.



The problem is, if I am assigning resources(work) to the projects, my custom
field (work)

should reflect the work, for example 10 days. But I first have to open every
single project

until my field shows the correct amount of days. Sometimes it is sufficient
if I just mark

the field.



Is anybody facing the same problem? Is there no point like "Refresh" or
something like that in Project?



Thanks



Maik
 
G

Gérard Ducouret

Hello Maik,
Where did you created your custom field ?
You have to copy the calculated field in all the projects : Master project
and all the sub-projects....
Tools / Organizer... / Fields

Tell us if it works.

Gérard Ducouret
 
M

Maik Richter

Thanks for your answer.

I created the field in the Masterproject. But the field
does not show up in the Organizer. Perhaps it is why
I have chosen the Field Name "Work".

But I tried this out without a positive result:
I created a "Duration" field and linked the
"Work" field into the "Duration" field. Then
I copied the "Duration" field into the sub-projects..
But as I mentioned, nothing changed.

Perhaps you got another idea?

If not, thank you for your answer..

Maik
 
G

Gérard Ducouret

It must work...
Please check that you are in Automatic Calculation :
Tools / Options / Calculation / Calculation Mode : Automatic.

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top