Maik Richter
Hi guys,
I created a Masterproject and added many Single-projects. The Masterproject
is connected with the Ressource Pool. I added a custom field (=Work) to the
Gantt Chart view.
The problem is, if I am assigning resources(work) to the projects, my custom
field (work)
should reflect the work, for example 10 days. But I first have to open every
single project
until my field shows the correct amount of days. Sometimes it is sufficient
if I just mark
the field.
Is anybody facing the same problem? Is there no point like "Refresh" or
something like that in Project?
Thanks
Maik
I created a Masterproject and added many Single-projects. The Masterproject
is connected with the Ressource Pool. I added a custom field (=Work) to the
Gantt Chart view.
The problem is, if I am assigning resources(work) to the projects, my custom
field (work)
should reflect the work, for example 10 days. But I first have to open every
single project
until my field shows the correct amount of days. Sometimes it is sufficient
if I just mark
the field.
Is anybody facing the same problem? Is there no point like "Refresh" or
something like that in Project?
Thanks
Maik