Actuals are changed when the plan is opened in the MSP client from

P

Pascal Jean

Hello,
I have one user with MSP Client 2003 on his workstation. He save his plan in
XML format and open it in MSP Client 2008.
We noticed that some actual are not the same in both environments.
I looked thru the parameters but I don’t find what could be the problem. Do
you already noticed this kind of problem?

Note that the problem doesn't appear when the plan is opened from a MPP file.

Thank you in advance
 
R

Rod Gill

What service pack levels are you on for 2003 and 2007? There have been a
number of xml bugs so this does not surprise me.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
P

Pascal Jean

Hello,
Thank you for this prompt answer. Here are the information from the "Help
about"
Office Project Client 2007: (12.0.6503.5000) SP2 MSO (12.0.6425.1000)
Office Project Client 2003: (11.2.2005.1801.15) SP2
 
P

Pascal Jean

Hello,
I'm looking in the ‘Resource Usage’ view, the Work and ‘Remaining Work’ are
sometimes different between 2003 and 2008. This is where I’m focusing now.
It doesn't happen for all the resources.
 