A
AmWall
Project Server 2007 pre-SP1
We are experiencing some random appearing taks updats:
Resources are entering time in PWA and its showing up as something different
(e.g., entered 40 hrs one day and it shows up on PWA as only 26). Then
someone hadn’t even put time in next week and 2 hours already shows up.
Any suggestions here?
We are experiencing some random appearing taks updats:
Resources are entering time in PWA and its showing up as something different
(e.g., entered 40 hrs one day and it shows up on PWA as only 26). Then
someone hadn’t even put time in next week and 2 hours already shows up.
Any suggestions here?