Actuals do not recalulate

S

ST

I'm using ms project with the option "ms project calculates cost" off.

If I then set the option "ms project calculates cost" it does not calculate
my actual costs, eventhough it warns me that it will once I click OK in the
options. In order for ms project to wake up and start calculating again, I
have to revise my manual entries and redo the task status (ie., by changing
actual, remaining, and/ or % complete). F9 does not help. Any ideas?

Using MS Project Pro 2003 sp2.
 