Actuals entered at the Top-Level of the project

R

Robert

Hello,



I was told that the OLAP cubes, the type of which is "Timesheet", take in
account, in the Actual Work or Actual Work Billable fields, the actuals
entered at the Top-Level of a project when the resource click Add Lines is
his/her timesheet. We tell the resources don't enter time at the top-level,
but many of them do that.

In fact, the Actual Work Billable field available in the EPM Timesheet cube
doesn't take in account the actual work entered at the Top-Level of the
project.

In the MSP_Project_Timesheet cube, the Actual Work and Actual Work Billable
fields don't take in account the actuals entered at the Top-Level of the
project.

So, how can we measure in the OLAP cubes, the actuals entered at the
Top-Level? Where are these actuals?

Thanks for any idea.
 