Actuals filled with planned (estimated) hours

J

Janis Krastins

hi,
One of the projects that is hosted on my MS Project Server is having
the following problem - for some tasks to which about 8 resources are
assigned the actual hours get filled with the planned hours per day,
although only two persons have reported actuals for this task. I did
some searching on the net and was not able to find anything helpful.
Has anyone had something similar? What's the cause?

sincerely,
Janis
 