actuals getting pushed into the future

  • Thread starter James from Sage
  • Start date
J

James from Sage

I'm using PWA 2003. I've noticed on a couple of occassions that after
updating the actuals - opening them in MS Project and than publishing - when
I next open the enterprise project in MS Project - they actuals have been
pushed out into the future.

After noticing this the first time, I always double-check the actuals before
publishing but it has still occurred a couple of times in the last few months.

I am able to fix this by resyncing the actuals but am not sure if doing so
changes what hrs are shown as approved on the timesheets.

Is this a kown issue?

Thanks,

- James
 
J

Jackson T. Cole

Did you go back to PWA to see if the pushed-out actuals were reflected in
timesheets after publishing?

Can't say I've seen this. I 've seen Work pushed out way nto the future,
but not actuals.

??????

JTC
 
J

James from Sage

Hi Jackson,

Thanks for the response!

The adjust actuals view still showed the correct actuals and the problem was
fixed with resyncing the actuals.

- James
 
J

Jackson T. Cole

So, once you resent actuals, the problem didn't show up again?

Strange ...!
 
J

James from Sage

That's right - it's only happened a handful of times in the past 4 months.
Last time it happened we were running out of space on our SQL Server - not
sure if that's related.
 