I'm using PWA 2003. I've noticed on a couple of occassions that after
updating the actuals - opening them in MS Project and than publishing - when
I next open the enterprise project in MS Project - they actuals have been
pushed out into the future.
After noticing this the first time, I always double-check the actuals before
publishing but it has still occurred a couple of times in the last few months.
I am able to fix this by resyncing the actuals but am not sure if doing so
changes what hrs are shown as approved on the timesheets.
Is this a kown issue?
Thanks,
- James
updating the actuals - opening them in MS Project and than publishing - when
I next open the enterprise project in MS Project - they actuals have been
pushed out into the future.
After noticing this the first time, I always double-check the actuals before
publishing but it has still occurred a couple of times in the last few months.
I am able to fix this by resyncing the actuals but am not sure if doing so
changes what hrs are shown as approved on the timesheets.
Is this a kown issue?
Thanks,
- James