Actuals in PWA vs. actuals in MS Project Pro

L

LimorS

After creating a project plan in Project Pro, I'm logging into PWA as a
resource (for test purposes) and enter working hours per task that the
resource is assigned to. After, I go through the approval process and
update the project plan. Actuals in project plan (duration & work) differ
from those in PWA. It makes me confused, because my project now does not show
the "real picture". Any help is greatly appreciated!
 
M

Mike Glen

Hi Limor,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
D

Dale Howard [MVP]

LimorS --

After updating the project plan with actuals, you need to click
Collaborate - Publish - All Information to "push" the latest schedule
changes to PWA. Many people miss this step, unfortunately, because the
publishing process is not automatic. Hope this helps.
 