After creating a project plan in Project Pro, I'm logging into PWA as a
resource (for test purposes) and enter working hours per task that the
resource is assigned to. After, I go through the approval process and
update the project plan. Actuals in project plan (duration & work) differ
from those in PWA. It makes me confused, because my project now does not show
the "real picture". Any help is greatly appreciated!