Actuals not shown Resource Availability view in PWA

M

murdoch

We are using Project Server 2003 and for all projects the actuals are nicely
in line between the project and the PWA ... except for 1. The actuals have
been entered, I acn see them everywhere except in the Resource Availability
view in the PWA. It used to work fine also for this particular project. I've
tried almost everything: overwrite actuals, adjust actuals, republish etc
 
D

Dale Howard [MVP]

murdoch --

Has the OLAP cube rebuilt since you made those changes? Remember, the
information on the View Resource Availability page is populated each time
the OLAP cube rebuilds. Hope this helps.
 
M

murdoch

Thanks for your reply. The cube rebuilds overnight and all other projects are
ok. What tables are used in the resource availability views in the PWA? Could
it be that these are corrupted/ not in line anymore with the timesheets?

BTW, if I plan, replan and publish, this info shows automatically in the
resource availability view while the olap cube builds only overnight!?
 